Here’s a look at work planned in the district for the week starting April 4, 2022. These schedules are subject to change due to weather conditions, equipment failure or other unforeseen issues. Motorists are advised to remain alert and pay special attention to all signs, barricades and traffic controls, and reduce their speed as they approach and travel through work zones. They should also avoid distractions such as cell phones, eating, drinking, or car audio or navigation systems.

Greenville Area (Hunt, Rains counties)

Sidewalk and Curb Ramp Project (several counties): The contractor has set barricades at the Wolfe City, Texas, location. The contractor is currently working on Santa Fe street and is near 50 percent complete. The project is moving towards the downtown area of Wolfe City. This project will improve pedestrian sidewalks and construct ADA-compliant curb ramps at these locations: Hunt County, SH 34 at Crockett Street to SH 34 at FM 816 in Wolfe City. Please be aware of workers and watch for work zones when traveling in this area.

FM 903, Rains County: From US 380 to FM 1560. The contractor has set barricades and bulletin boards and advance warning signs. The contractor has begun hauling new flexbase and placing new geogrid and cement treated the material. Culvert walls are being constructed and poured. The contractor reworked base and built subgrade approximately 1,400 feet. The contractor also poured a parallel wall.

FM 275, Rains County: from SH 19 to FM 514. The contractor has been doing the finish work on the cement-treated flexbase, driveways and backfilling from Lake Fork Creek to the north for one mile. Drill shaft installation has been completed and beams will be set soon. The contractor has completed the 150-foot bridge deck pour, as well as setting SET’s and driveway pipe on the north and south side of the project. The bridge crew is currently installing the bridge rail and are scheduled to complete this task this week. Please be aware of lane closures, detours, and watch for work zones and workers when traveling in this area.

SH 276, Hunt County: from FM 36 to SH 34 (Quinlan Bypass). The contractor has placed project barricades and has prepared and cleared the right-of-way. The contractor has performed a traffic switch for northbound and southbound traffic on Spur 264 to complete the concrete pavement on the east half of Spur 264. The contractor continues grading flexbase on SH 276 from east of the bridge approach to the proposed CRCP section, fine grade embankment work on the west end of the project, and prep work for geo-grid and flexbase. Please be aware of lane closures and watch for work zones and workers when traveling in this area.

FM 1566, Hunt County: from FM 272 near Celeste to State Highway 34. The contractor has placed prime coat on the beginning mile. Prep work for temporary strip should be placed late next week for the first-mile section. Contractor is working on backfilling shoulders and repairing silt fences along the left and right sides of miles 1 and 2.

Maintenance crews in Hunt County will be performing overlay operations on FM 1570 from I-30 to SH 66, and on FM 118 from SH 224 to FM 512. Crews will be performing potholing at various locations in Hunt County. Maintenance contract crews will be performing debris removal on I-30 and guard rail repair at various locations around Hunt County. Please be careful when traveling in these areas, watch out for workers and maintain a safe distance from work crews.

Maintenance crews in Rains County will be performing seal coat prep work on the I-30 south frontage road from CR 3102 to FM 1737. Crews will be performing various sign installations, potholing, edging, and debris removal. Maintenance crews will be performing herbicide operations on various roadways. Please watch for lane closures, work zones and workers along the roadway, and maintain a safe distance from work crews.